Dears,
we are using average costing for the Raw materials and finished Products,the issue we are facing is that when we issue raw materials (migo) to the process order with Quantity of raw materials more than the amount defined in the BOM of the Finshed prodcut ,the cost is calculated using the Quantity found in the BOM and not the actual Quantity Issued. We need to solve this issue so that the process order carry the real cost of the new Quantity
Thanks,
Request clarification before answering.
Hello,
Please check your settings of your valuation variant-->Material Valuation-->Strategy sequence and select "Price from Preliminary Order Cost Est(Goods Receipt only)" for Priority 1.
Regards,
Naveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 57 | |
| 29 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.