Hello

I'm testing with a work center which is already overloaded in the whole year. When I try to create a production order again on that work center, there is a popup message saying Capacity Availability  is a problem and I have to reschedule it with a button called "finite scheduling". Then the "operation dates" window comes out. With this window how can I make an automatic rescheduling to the earliest available date on the work center?

milk

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Likes

Milk,

When you click on finite scheduling during order creation system would automatically schedules and shifts the dates based on the overall profile you assigned in OPJK.

Br

KK

Former Member
0 Likes

hello Kumar

I'm using SAPMPSG006 at order creation but the order is not automatically rescheduled to a proper date...

Former Member
0 Likes

Milk,

You need to check the time profile you are using,if capacity is not available in given time range then system would not schedule the order and gives message saying capacity is not available.


What is message you are getting check the scheduling log.

And SAP recommends to use profile SAPSFCG013 for production orders capacity check.

Check below SAP notes for production order capacity check functionality.

160613 - Capacity check: Capacity availability check

159337 - Capacity Check: Basic Load

Br

KK

Former Member
0 Likes

Very useful information Kumar. Thanks.

Somehow I'm still not get my production order scheduled automatically even with standard profile SAPSFCG013...

Former Member
0 Likes

Milk,

Please note order will not be automatically scheduled you need to click on finite scheduling then system would schedules the order on available capacity days.

Br

KK