Hello
I'm testing with a work center which is already overloaded in the whole year. When I try to create a production order again on that work center, there is a popup message saying Capacity Availability is a problem and I have to reschedule it with a button called "finite scheduling". Then the "operation dates" window comes out. With this window how can I make an automatic rescheduling to the earliest available date on the work center?
milk
Request clarification before answering.
Milk,
When you click on finite scheduling during order creation system would automatically schedules and shifts the dates based on the overall profile you assigned in OPJK.
Br
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Milk,
You need to check the time profile you are using,if capacity is not available in given time range then system would not schedule the order and gives message saying capacity is not available.
What is message you are getting check the scheduling log.
And SAP recommends to use profile SAPSFCG013 for production orders capacity check.
Check below SAP notes for production order capacity check functionality.
160613 - Capacity check: Capacity availability check
159337 - Capacity Check: Basic Load
Br
KK
| User | Count |
|---|---|
| 14 | |
| 13 | |
| 7 | |
| 7 | |
| 5 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.