Hi, I am running activity confirmation,i am having following questions
1. i know activity is 0040. With this how i can find network order? i am unable to find network order by using table AFVC.
2 In which table we can see the price of activity confirmation ?
Please help me
thank you
Request clarification before answering.
Hi Hemu,
Input WBS and activity number in AFVC to get internal number of network (AUFPL). Put this internal number in AFKO or AUFK to get network number.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anji,
I don't think you will see the cost posted in COSP or RPSCO just after confirmation. The confirmation details will be in AFRU table. You can get the confirmation details by entering the Order #( AFRU-AUFNR) and Operation #(AFRU-AUFPL).
after getting the hrs confirmed from this table, you need to calculate the cost by multiplying it with the Activty Price.
The COSP or RPSCO will have the cost , if there's any time entry posted against NWA and CATA
Hi
I enterd the follwing data for table RPSCO,COSP. Also i am not able to see cost of activity confirmation.
COSP table
Ledger 0
Object number
Fiscal Year 2013
Value Type 4
Version 0
Cost Element 619000
CO subkey
Bus.Transaction RKL
Trading Partner
Trdg part.BA
Dr/Cr indicator D
Trans. Currency EUR
Period bloc
Debit type 1
Functional Area
Width of Output List 50
Maximum No. of Hits 200
RPSCO TABLE
Obj.no. NP000000
Ledger 0000
Value Type 4
Object ind.
Fiscal Year 2013
Val.category
Budget Type
Version 0
Category
Fund
Trans. Currency EUR
Period block
Width of Output List
Maximum No. of Hits
mum No. of Hits
Please tell me
thank you
Hi Hemu,
If you want to get the actual cost of activity confirmation from RPSCO table follow this,
1) In AFVC table enter the WBS under which the said activity falls. Execute it. You will get a llist of all the activities that belong to the WBS you entered.
2) Select the object number of the activity in question. Copy it.
3) Input the object number of this activity in the RPSCO table and choose value type as 4. You can also choose the budget type as RKL (CO Actual activity allocation).
4) Execute it. You should get the actual cost of activity confirmation.
Revert if this works.
Regards,
Gokul
Activity #AFVC-VORNR and the OBJNR for the same is AFVC-OBJNR
AFRU is the table for confirmation. The price should be to be from COSP or need to be calculated based on confirmed hrs and activity price
psconsultant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
1.Activity #AFVC-VORNR and the OBJNR for the same is AFVC-OBJNR
By this answer i unable to network
2.AFRU is the table for confirmation. The price should be to be from COSP or need to be calculated based on confirmed hrs and activity price
By this answer also i unable to find actual cost on activity.for getting actual cost which fields i have to select in COSP.
Please help me
thank you
| User | Count |
|---|---|
| 13 | |
| 13 | |
| 6 | |
| 6 | |
| 4 | |
| 4 | |
| 4 | |
| 2 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.