Hello,

I need data action to copy data from input template to SAC story (Planning model.). Only challenge I am facing how to map start date and end date and populate amounts to Periods . Please see below example.

Date granuality is YYYYMM. 

Input template:

AccountCost CenterSPeriodTperiodAmount
61061000101013012025072025091000
61061000171013012025102025122000
61020000101013012025082025105000
61020000171013012025072025096000

Target:

AccountCost CenterP1P2P3P4P5P6P7P8P9P10P11P12
6106100010101301      100010001000   
6106100017101301         200020002000
6102000010101301       500050005000  
6102000017101301      600060006000   

Hello Thomas,

Input template is on model1 and target split to periods is on model2 i.e. different models for source and target. 

Version is same only .

2 REPLIES 2
Read only

ThomasK
Active Participant
0 Likes
1,052

Hi @sumeet1987 , is the "input template" data in an XLS to upload or is it already imported data which is in the same data model but in a different version?

Read only

0 Likes
1,041

Hello Thomas,

Input template is on model1 and target split to periods is on model2 i.e. different models for source and target. 

Version is same only .