2025 Oct 02 12:39 PM
Hello,
I need data action to copy data from input template to SAC story (Planning model.). Only challenge I am facing how to map start date and end date and populate amounts to Periods . Please see below example.
Date granuality is YYYYMM.
Input template:
| Account | Cost Center | SPeriod | Tperiod | Amount |
| 61061000 | 10101301 | 202507 | 202509 | 1000 |
| 61061000 | 17101301 | 202510 | 202512 | 2000 |
| 61020000 | 10101301 | 202508 | 202510 | 5000 |
| 61020000 | 17101301 | 202507 | 202509 | 6000 |
Target:
| Account | Cost Center | P1 | P2 | P3 | P4 | P5 | P6 | P7 | P8 | P9 | P10 | P11 | P12 |
| 61061000 | 10101301 | 1000 | 1000 | 1000 | |||||||||
| 61061000 | 17101301 | 2000 | 2000 | 2000 | |||||||||
| 61020000 | 10101301 | 5000 | 5000 | 5000 | |||||||||
| 61020000 | 17101301 | 6000 | 6000 | 6000 |
2025 Oct 03 12:40 PM
Hi @sumeet1987 , is the "input template" data in an XLS to upload or is it already imported data which is in the same data model but in a different version?
2025 Oct 03 2:12 PM
Hello Thomas,
Input template is on model1 and target split to periods is on model2 i.e. different models for source and target.
Version is same only .