‎2009 Nov 02 9:14 PM
Hi All,
We had a new report development and everthing developed as local object. Inside this report we were using 2 includes.
Later we attached the report to TR 3216. But forgot to attach Include to TR3216.So while transporting to Quality , it end in error
TR3216 Details
R3TR PROG ProgXYZ
Later we attached includes to TR 3222. Also attached the program and texts.
TR3222 Details
LIMU REPS ProgXYZ
LIMU REPT ProgXYZ
R3TR PROG Include abc
R3TR PROG Include def
R3TR TRAN Transaction of prog XYZ
Now we have everthing in quality. My question is,to transport it to production we have to move the TR's ( 3216 ,3222) in this specific order.
or TR3222 itself is ok as it contains everything, (But LIMU DYNP is missing)
Regards,
Nikhil
‎2009 Nov 02 9:43 PM
You need to move both the transports to the production in the order 3216 and 3222.
3216 has the dependency with 3222.
So you need to request the basis team to transport both the transports and in order 3216,3222
‎2009 Nov 03 4:08 AM
Hello Nikhil
Using transaction STMS you can import multiple requests at the same time. Thus, if your basis team select both requests and imports them simultaneously this means they are transported as a "virtual" single request. The import order does not play any role here.
Regards
Uwe
‎2010 Aug 16 2:11 PM