Can anybody please tell me what are the tables for getting the requirement quantity field which we see in MD04 for any material. The requirement may be for as we see in MD04

OrdRes: means that the material will be used in a process order that has been created and the demand is very near

DepR: means that the material will be used, but the process order has not been created yet. A planned order for the fininshed product exists.

Dlvy: means that the material is being transferred to another area

PlORel: means that the material has been ordered on a stock transport order

Thanks,

Bob.

Hi All,

Can anybody please tell me what are the tables for getting the requirement quantity field which we see in MD04 for any material. The requirement may be for as we see in MD04

OrdRes: means that the material will be used in a process order that has been created and the demand is very near

DepR: means that the material will be used, but the process order has not been created yet. A planned order for the fininshed product exists.

Dlvy: means that the material is being transferred to another area

PlORel: means that the material has been ordered on a stock transport order

Thanks,

Bob.

1 REPLY 1
Read only

Former Member
0 Likes
1,224

hi check the tables..for planned orders

PLAF and RESB

the material (product no) coming from the table MARA

regards,

venkat