Dear all

We are going to copy the PRD system to the Quality System. At the moment our problem is who we could preserve all the RFC that we have in the Quality System.

It's possibel to download all the RFC and then Upload it.

Best Regards

Thanks In advanced

Dear all

We are going to copy the PRD system to the Quality System. At the moment our problem is who we could preserve all the RFC that we have in the Quality System.

It's possibel to download all the RFC and then Upload it.

Best Regards

Thanks In advanced

6 REPLIES 6
Read only

Former Member
0 Likes
973

Hi

<b>RFC's are client Independent</b>

there is no need to worry about them when you are copying PRD to QAS

No ned of downloading the RFC's and Uplaoding the same.

<b>Reward points for useful Answers</b>

Regards

Anji

Read only

Former Member
0 Likes
973

hI,

RFC is an SAP interface protocol. Based on CPI-C, it considerably simplifies the programming of communication processes between systems

<b>Reward points</b>

Regards

Read only

Former Member
0 Likes
973
Read only

Former Member
0 Likes
973

After the copy of the PRD system to Quality System. We need to do the following steps:

1 - Delete all irrelevant in SM59

2 - Recreate all the entry’s in SM59 that we in the Quality Before the Copy.

Because we have a Big system and we have a loot of connections (SM59) we what to know if is possible to do the step 2 (in another way rather then manual). for example Export and then import the tables RFC*

Those any one could you indicate the tables that we need to Export/Import? Or other way to this?

Best Regards

Read only

0 Likes
973

Hi,

It´s necessary to recreate the RFC connections when It´s realized a client copy over differents systems?

More thanks

Read only

0 Likes
973

Hi Pedro Coelho Rodrigues

Most of the time when you move transport or Test from DEV >QAS> PRD Config and setting will be same almost

In you case when you refreshing with PRD TO QAS then you no need to do any Changes to RFC Destination as long as QAS & PRD in Syncronization...

if QAS & PRD Not in sync.... Create entries QAS Then Refresh QAS System.

Destination table for Remote Function Call :RFCDES

I hope this help you

Note: RFC Destination Setting are client Independent.

Thanks

Ramesh