Hi

I have a situation where i executed BD21 for changes to materials but no idocs were created due to some issue with the distribution model. Now i have fixed the issue and would like to re process all the materials which were changed. Since i have already executed BD21, now no new idocs are being generated. Is there a way to reprocess the changed materials and generate the idocs again.

Thanks

Nag

4 REPLIES 4
Read only

roger_gomez
Active Participant
0 Likes
836

Hi Nag,

If you are allowed to do it, find your messages in NAST table and blank the AKTIV indicator. BD21 will select again that messages.

Roger

Read only

roger_gomez
Active Participant
0 Likes
836

Maybe you can use RSNAST00 program (enabling "Send again" checkbox) to reprocess the matmas messages.

Reward points if useful.

Roger

Read only

0 Likes
836

Hi Roger

Thanks for your inputs. I am trying to generate idocs through the change pointers and not using output determination.

When i executed BD21 the first time, idocs were not generated due to some config issues. But the job ended successfully saying that idocs were generated and marked all the changed material documents under change pointers (But in WE02, the idocs never showed up actually).

Now i have fixed the issue in config and want to generate the idocs using the change pointers. Is there any way to regenerate the same idocs using BD21 or some alternative.

Thanks

Nag

Read only

0 Likes
836

Run RBDMIDOC.