2009 Sep 01 1:12 PM
Hello Gurus,
I have a problem concerning the status of release strategy of my POs.
I have a PO which when I modify it triggers automatic release and BAPI_PO_RELEASE is used successfully.
Now when the save process is over and the I go to the release strategy tab, none of my status are set correctly. The first one has a warning sign and the others are blank, just as if no modification were made.
However, if I edit the same PO or re-open the PO, the status are correct this time. It seems that the status are not getting refreshed appropriately.
What can i do to solve this issue?
Thanks a lot
Parvez
Hello Gurus,
I have a problem concerning the status of release strategy of my POs.
I have a PO which when I modify it triggers automatic release and BAPI_PO_RELEASE is used successfully.
Now when the save process is over and the I go to the release strategy tab, none of my status are set correctly. The first one has a warning sign and the others are blank, just as if no modification were made.
However, if I edit the same PO or re-open the PO, the status are correct this time. It seems that the status are not getting refreshed appropriately.
What can i do to solve this issue?
Thanks a lot
Parvez
2009 Sep 01 2:13 PM
Hi, sometimes you have to call BAPI_TRANSACTION_COMMIT (or just COMMIT WORK) after calling a BAPI. So although the execution of the BAPI is correct the data is not stored/updated.