2007 Jul 19 10:42 AM
Hi Experts,
I tried to create a purchase order on 31.01.2007 with payment term ZB11, but I couldnt and I got the following error Error in net price calculation as February is having 28 days. The problem only exists one day in a year i.e. on 31.01.2007 only.
Here payment term details are given below.
ZB11 is defined as providing a discount of 3% for 30 days from the Baseline date and 0% from the 1 day of the next to next month (where baseline date is the document date). In ZB11, Fixed date is 1 and Additional months are 2 for second term. Please give me a solution ASAP.
Thanks in advance
2007 Jul 19 12:30 PM
Hi
Since the Payment terms ZB11 are defined like 3% for 30 days discount and the dates are given from 1st to 30 days, since Feb is 28 days only it s giving error
so take the help of a FI functional consultant in this regard or use someother payment terms and create the PO
<b>Reward points for useful Answers</b>
Regards
Anji
Hi Experts,
I tried to create a purchase order on 31.01.2007 with payment term ZB11, but I couldnt and I got the following error Error in net price calculation as February is having 28 days. The problem only exists one day in a year i.e. on 31.01.2007 only.
Here payment term details are given below.
ZB11 is defined as providing a discount of 3% for 30 days from the Baseline date and 0% from the 1 day of the next to next month (where baseline date is the document date). In ZB11, Fixed date is 1 and Additional months are 2 for second term. Please give me a solution ASAP.
Thanks in advance
2007 Jul 19 12:30 PM
Hi
Since the Payment terms ZB11 are defined like 3% for 30 days discount and the dates are given from 1st to 30 days, since Feb is 28 days only it s giving error
so take the help of a FI functional consultant in this regard or use someother payment terms and create the PO
<b>Reward points for useful Answers</b>
Regards
Anji