‎2009 Mar 11 2:22 PM
Hi all,
i am using one report,
where one user already created one variant.
Now his requirement is to chabge vallues of variant.
How can i do this to same variant, and after my changes when ever he selcts the variant , it should con
‎2009 Mar 11 2:28 PM
hi,
its very simple,
1. Execute the report
2. open the variant which was created.
3. change the required values which ever user wants to.
4. click on save button.
5. click on save button again.
6. it will prompt for overwriting the variant. select yes.
7. its done.........
Regards,
Siddarth
‎2009 Mar 11 2:59 PM
Hi siddharth,
thank u vry much..
its solve and its really simple
‎2009 Mar 11 3:22 PM
Hi,
*To Moderators :*
" Is it fine if I ask for rewards if the problem is solved with answer I give. Please let me know
‎2009 Mar 11 3:31 PM
It's not.
The purpose of the forum is the exchange of ideas, not the accumulation of points.
Rob
Edited by: Rob Burbank on Mar 11, 2009 11:32 AM
‎2009 Mar 11 3:38 PM
‎2009 Mar 11 3:39 PM
To add to what Rob said. It is also part of the Rules of Engagement to award points to answers which have been useful to the original poster. If someone consistently doesn't award points, then please let the moderators know by using the "abuse" button. I usually find that reminding the member with a polite email usually does the trick.