Regarding CO03

Former Member
0 Likes
1,217

Hi when i go to the transaction CO03 and give the order number with radiobutton dusplay overview ticked

and press enter. then in the next screen goto -> costs->analysis in the output we get

Target/Actual quantity variants i want to know the report name which is giving this value.

Thanks in advance

1 ACCEPTED SOLUTION
Read only

Former Member
0 Likes
1,152

Check Tables COSB , COSP , COSS , COST

Hi when i go to the transaction CO03 and give the order number with radiobutton dusplay overview ticked

and press enter. then in the next screen goto -> costs->analysis in the output we get

Target/Actual quantity variants i want to know the report name which is giving this value.

Thanks in advance

8 REPLIES 8
Read only

GauthamV
Active Contributor
0 Likes
1,152

check AFPO table.

Read only

Former Member
0 Likes
1,152

THANKS FOR YOUR RESPONSE. But i need the table and filed which fill the column Target/actual quatity variance in the output when we execute co03 and goto->cost analysis

Read only

Former Member
0 Likes
1,152

tHANKS FOR YOUR RESPONSE .

i need how the calculation of fields in the columns target/actual quatity variance are being calculated

this field have to be selected from layout .ia there any functionmodule????? to calculate this column

please let me know

Read only

Former Member
0 Likes
1,152

can anyone please give the calculation logic for Target/Actual quantity variance column whcih have to be selected in the layout when co03 is executed and goto->cost analaysis select this field from the layout.

Thanks in advance

Read only

Former Member
0 Likes
1,152

It's a function module.

'CO_COST_SHOW_ORDER_COSTS'

Read only

0 Likes
1,152

THANKS FOR YOUR RESPONSE. But i need the table and filed which fill the column Target/actual quatity variance in the output when we execute co03 and goto->cost analysis

Read only

0 Likes
1,152

Hello ,

Debug the Program U will come to know easily about the Filed and Table information of the required field.

Regards

Read only

Former Member
0 Likes
1,153

Check Tables COSB , COSP , COSS , COST