If I want any changes to a PO e.g. qty, value, cost centres, account assignments, text etc to trigger a new release, how can I do this, config or ABAP?
Could you please let me know.
If I want any changes to a PO e.g. qty, value, cost centres, account assignments, text etc to trigger a new release, how can I do this, config or ABAP?
Could you please let me know.
2007 Jun 18 7:42 AM
hi,
go to T.coe me22 there u can provide your po numer for that u can change and save.
reward points if helpful,
regards,
seshu.
2007 Jun 18 7:59 AM
2007 Aug 18 4:23 PM
Hi Sumit,
You have to sit with functional consultant, in the configuration, there is setting when you change the PO, it will reset the release.
Regards,
Manoj
2007 Jun 18 7:48 AM
Hi,
The difference is that the 'N' transaction use Enjoy SAP controls (as of 4.6C I beleive). As a result of this you cannot perform a BDC Recording with these 'N' transactions.
<b>Reward points</b>
Regards
2007 Aug 19 2:13 AM
Purchase Order release strategies are set in customizing. You can configure what changes to the order require re-release and which ones dont (eg tolerance on amount).
Talk to an MM functional consultant.
NB: These are a pain to change sometimes, as not all parts get transported and must be done in each system / client.