PO release

Former Member
0 Likes
697

If I want any changes to a PO e.g. qty, value, cost centres, account assignments, text etc to trigger a new release, how can I do this, config or ABAP?

Could you please let me know.

If I want any changes to a PO e.g. qty, value, cost centres, account assignments, text etc to trigger a new release, how can I do this, config or ABAP?

Could you please let me know.

5 REPLIES 5
Read only

Former Member
0 Likes
678

hi,

go to T.coe me22 there u can provide your po numer for that u can change and save.

reward points if helpful,

regards,

seshu.

Read only

0 Likes
678

Thanks, but how will that trigger a new release

Read only

0 Likes
678

Hi Sumit,

You have to sit with functional consultant, in the configuration, there is setting when you change the PO, it will reset the release.

Regards,

Manoj

Read only

Former Member
0 Likes
678

Hi,

The difference is that the 'N' transaction use Enjoy SAP controls (as of 4.6C I beleive). As a result of this you cannot perform a BDC Recording with these 'N' transactions.

<b>Reward points</b>

Regards

Read only

Former Member
0 Likes
678

Purchase Order release strategies are set in customizing. You can configure what changes to the order require re-release and which ones dont (eg tolerance on amount).

Talk to an MM functional consultant.

NB: These are a pain to change sometimes, as not all parts get transported and must be done in each system / client.