Someone could teach how to measure the quantity of objects been modified in a range of dates?
We need to know how many objects are been modified, with the proposal to measure if the implementation of a project is getting end.
I believe if we have the modified objects decreasing that´s probable that are getting end of the implementation. Am i right?
2012 May 29 5:49 PM
You can view the transports from se03 for each object ( data element,funcitons,program etc ) and filter it accordingly. You have the option to provide the date range. The output list will not excatly give you the solution. But it helps.
2012 May 29 2:50 PM
This sounds like a very unusual means to estimate the status of an implementation project. Can't your team leaders report the current status?
Other than that, table VRSD give a good overview over what has been recently released from the development system.
Thomas
2012 May 29 5:49 PM
You can view the transports from se03 for each object ( data element,funcitons,program etc ) and filter it accordingly. You have the option to provide the date range. The output list will not excatly give you the solution. But it helps.