HI,
I got a report, which reschedules the schedule lines and creates new schedule lines if required for a material on MRP date by using FM BAPI_SCHEDULE_MAINTAIN.
Here i am facing one issue for a specific material i dont have any schedule lines and i have demand based on that i need to create new schedule lines.
with the above FM i am unable to create,
can any one help me on this...
HI,
I got a report, which reschedules the schedule lines and creates new schedule lines if required for a material on MRP date by using FM BAPI_SCHEDULE_MAINTAIN.
Here i am facing one issue for a specific material i dont have any schedule lines and i have demand based on that i need to create new schedule lines.
with the above FM i am unable to create,
can any one help me on this...
2013 Feb 28 1:07 PM
2013 Mar 04 8:02 AM
Thanks for your reply..
Issue got resolved and i am able to create schedule lines now...