2010 Jan 27 9:19 AM
Hi Experts,
I am creating routing using bapi BAPI_ROUTING_CREATE. In that i am passing header,operation and componenet
allocation level but its giving error as 'operation has to be assigned is not completely specified'. Kindly anyone help me regarding this..
Thanks
Ramesh Manoharan
Edited by: ramesh.manoharan on Jan 30, 2010 4:10 PM
hello if the problem is with operation...then pass the below data for header and operation it creates routing i have verified.....
Populate BAPI_ROUTING_CREATE .....using following structures and fields
BOMUSAGE 1
TASK
GROUP_COUNTER 1
TASK_LIST_USAGE 1
TASK_LIST_STATUS 4
TASK_MEASURE_UNIT EA
LOT_SIZE_FROM 190
LOT_SIZE_TO 300
DESCRIPTION TEST123
OPERATION
GROUP_COUNTER 1
ACTIVITY 0010(operation number)
CONTROL_KEY PP01
PLANT 0001
DESCRIPTION TEST
OPERATION_MEASURE_UNIT EA
DENOMINATOR 1
NOMINATOR 1
BASE_QUANTITY 12
after this dont forget to use BAPI_TRANSACTION_COMMIT ( go to se37 ..test-test sequences---enter BAPI_ROUTING_CREATE and BAPI_TRANSACTION_COMMIT)
and execute ..i have tested this it works perfet..create routing with 1 opeartion 0010...
for componenet allocation i am looking..but i have some access problems ......as u said u have error in opeartin that means what ever data you are using for COMPONENETALLOCATION is correct.
first create one routing with header and one operation only using data i have specified...if it works then for next routing u can add fields into componenent allocation and test.....remember for componenet allocation..BOM needs to be there for that material assigned.
hope i am able to clear some of your confusion..cheers....
-
Abhijeet
2010 Feb 01 2:14 AM
chk this link for sample pgm
http://www.sapnet.ru/viewtopic.php?t=1951&sid=520e3db2937fef4ed18117f320f9539e
2010 Feb 02 5:01 AM
Hi,
The link which you have been sent is not helping for me .. In that program the component allocation structure has not been
populated. I want to know the details about each field in structure of component allocation... kindly help me regarding this.
Thanks
Ramesh Manoharan
2010 Feb 02 10:52 AM
hello ramesh,
i will provide you the field and structures which should be populated to create routing through BAPI_ROUTING_CREATE
in few minutes for sure.cause i am checking it.
till the time i can give you a hint..try this hint....
go to CA01 (create routing) create routing through this ....with header,one operation and one componenet allocation.....
ask any of the functional consultant to create this if its not possible for you as a ABAPER....
then take that routing number and go to BAPI_ROUTING_DISPLAY.....provide that number to this BAPI and execute...
what ever export structures you will be getting for header,operation and componenet allocation..pass the same
structures and values to BAPI_ROUTING_CREATE...so by that means u will be able to create routing....
here few things are important...
materail creation in the plant specified...
as you are getting error in opeartion check work center........
and for componenet alllocation BOM should have been in the system for that material.....
2010 Feb 02 11:40 AM
hello if the problem is with operation...then pass the below data for header and operation it creates routing i have verified.....
Populate BAPI_ROUTING_CREATE .....using following structures and fields
BOMUSAGE 1
TASK
GROUP_COUNTER 1
TASK_LIST_USAGE 1
TASK_LIST_STATUS 4
TASK_MEASURE_UNIT EA
LOT_SIZE_FROM 190
LOT_SIZE_TO 300
DESCRIPTION TEST123
OPERATION
GROUP_COUNTER 1
ACTIVITY 0010(operation number)
CONTROL_KEY PP01
PLANT 0001
DESCRIPTION TEST
OPERATION_MEASURE_UNIT EA
DENOMINATOR 1
NOMINATOR 1
BASE_QUANTITY 12
after this dont forget to use BAPI_TRANSACTION_COMMIT ( go to se37 ..test-test sequences---enter BAPI_ROUTING_CREATE and BAPI_TRANSACTION_COMMIT)
and execute ..i have tested this it works perfet..create routing with 1 opeartion 0010...
for componenet allocation i am looking..but i have some access problems ......as u said u have error in opeartin that means what ever data you are using for COMPONENETALLOCATION is correct.
first create one routing with header and one operation only using data i have specified...if it works then for next routing u can add fields into componenent allocation and test.....remember for componenet allocation..BOM needs to be there for that material assigned.
hope i am able to clear some of your confusion..cheers....
-
Abhijeet
2010 Feb 02 1:02 PM
Hi
Thanks for the reply .. I am getting error in component level. I have tested for only header and operation level it is working fine.
but when i pass component structure to bapi it is giving error as 'The component to be assigned has not been completely
specified'. Could you describe about each field in component allocation level..
Thanks
Ramesh Manoharan
2013 Jul 15 7:11 AM
The error you are getting is coming from component allocation.
Ensure that the structure and internal table for component allocation (passed to BAPI) is cleared before being populated.
componentallocation-valid_from
componentallocation-valid_to_date '.
"make sequence 6 characters
COMPONENTALLOCATION-SEQUENCE_NO = lv_sequence.
COMPONENTALLOCATION-ALTERNATIVE_BOM = gs_stko-stlal.
COMPONENTALLOCATION-BOM_NO = gs_stko-stlnr.
COMPONENTALLOCATION-BOM_TYPE = gs_stko-STLTY.
COMPONENTALLOCATION-bom_type_root = gs_stko-STLTY.
COMPONENTALLOCATION-BOM_NO_ROOT = gs_stko-stlnr.
COMPONENTALLOCATION-ITEM_ID = gs_stpo-STLKN.
componentallocation-activity = VORNR.
componentallocation-item_no = POSNR.
COMPONENTALLOCATION-PLANT = WERKS.
COMPONENTALLOCATION-MATERIAL = MATNR.
COMPONENTALLOCATION-COMP_QTY = gs_stpo-MENGE.
COMPONENTALLOCATION-COMP_UNIT = gs_stpo-MEINS.
This should help. It is working for me.