Hello Gurus,

I am using following function module to add 10 days to current sy-datum. So if the current date is 08/18, then I want certain things to be done on 08/28. But this adds straight 10 days to current sy-datum. I want the system to add 10 business days.

Is there any function module for this ?

Regards,

Tushar.

1 ACCEPTED SOLUTION
Read only

Former Member
0 Likes
3,444

Hi,

try these function module

1>

BKK_ADD_WORKINGDAY

IMPORTING

VALUE(I_DATE) TYPE SY-DATUM

VALUE(I_DAYS) TYPE I

VALUE(I_CALENDAR1) TYPE TFACD-IDENT OPTIONAL

VALUE(I_CALENDAR2) TYPE TFACD-IDENT OPTIONAL

EXPORTING

VALUE(E_DATE) TYPE SY-DATUM

VALUE(E_RETURN) TYPE SY-SUBRC

2>

FKK_ADD_WORKINGDAY

IMPORTING

VALUE(I_DATE) TYPE SY-DATUM

VALUE(I_DAYS) TYPE I

VALUE(I_CALENDAR1) TYPE TFACD-IDENT OPTIONAL

VALUE(I_CALENDAR2) TYPE TFACD-IDENT OPTIONAL

EXPORTING

VALUE(E_DATE) TYPE SY-DATUM

VALUE(E_RETURN) TYPE SY-SUBRC

3>

WDKAL_DATE_ADD_FKDAYS

IMPORTING

VALUE(I_DATE) LIKE SY-DATLO

VALUE(I_FKDAY) LIKE MDCAL-FKDAY

VALUE(I_FABKL) LIKE TFACD-IDENT

EXPORTING

VALUE(E_DATE) LIKE SY-DATLO

VALUE(E_FKDAY) LIKE MDCAL-FKDAY

EXCEPTIONS

ERROR

Regards,

Anirban

Hello Gurus,

I am using following function module to add 10 days to current sy-datum. So if the current date is 08/18, then I want certain things to be done on 08/28. But this adds straight 10 days to current sy-datum. I want the system to add 10 business days.

Is there any function module for this ?

Regards,

Tushar.

5 REPLIES 5
Read only

Former Member
0 Likes
3,445

Hi,

try these function module

1>

BKK_ADD_WORKINGDAY

IMPORTING

VALUE(I_DATE) TYPE SY-DATUM

VALUE(I_DAYS) TYPE I

VALUE(I_CALENDAR1) TYPE TFACD-IDENT OPTIONAL

VALUE(I_CALENDAR2) TYPE TFACD-IDENT OPTIONAL

EXPORTING

VALUE(E_DATE) TYPE SY-DATUM

VALUE(E_RETURN) TYPE SY-SUBRC

2>

FKK_ADD_WORKINGDAY

IMPORTING

VALUE(I_DATE) TYPE SY-DATUM

VALUE(I_DAYS) TYPE I

VALUE(I_CALENDAR1) TYPE TFACD-IDENT OPTIONAL

VALUE(I_CALENDAR2) TYPE TFACD-IDENT OPTIONAL

EXPORTING

VALUE(E_DATE) TYPE SY-DATUM

VALUE(E_RETURN) TYPE SY-SUBRC

3>

WDKAL_DATE_ADD_FKDAYS

IMPORTING

VALUE(I_DATE) LIKE SY-DATLO

VALUE(I_FKDAY) LIKE MDCAL-FKDAY

VALUE(I_FABKL) LIKE TFACD-IDENT

EXPORTING

VALUE(E_DATE) LIKE SY-DATLO

VALUE(E_FKDAY) LIKE MDCAL-FKDAY

EXCEPTIONS

ERROR

Regards,

Anirban

Read only

Former Member
0 Likes
3,444

Hi,

Try this-

CALL FUNCTION 'BKK_ADD_WORKINGDAY'
  EXPORTING
    i_date            = i_date
    i_days            = i_days
*   I_CALENDAR1       = I_CALENDAR1
*   I_CALENDAR2       = I_CALENDAR2
* IMPORTING
*   E_DATE            = E_DATE
*   E_RETURN          = E_RETURN

Regards,

Sujit

Read only

santhosh_patil
Contributor
0 Likes
3,444

Hi,

Check this two FM

DATE_CONVERT_TO_FACTORYDATE

FACTORYDATE_CONVERT_TO_DATE

---Patil

Read only

former_member585060
Active Contributor
0 Likes
3,444

Try

RP_CALC_DATE_IN_INTERVAL

Read only

Former Member
0 Likes
3,444

Hope these FMs help.

Use them as per you requirement

FACTORY_CALENDAR_ATTRIBUTE_GET Get Logistics Calendar Attributes (Table TFACD)

FACTORY_CALENDAR_GET

DATE_CONVERT_TO_FACTORYDATE Returns logistics calendar date for a date

FACTORYDATE_CONVERT_TO_DATE Returns date for a logistics calendar date

LAST_FACTORYDATE_GET Calendar function: Return last factory date for a logistics calendar