2010 Feb 04 6:39 AM
Hi,
whenever there is a change in the Material Characteristics I need to send the details to another system, we can achive this using Change Pointers but while sending I need to add some extra conditions and change the values as per the conditions where can I do this changes, I have searched for exit in the RBDMIDOC but could not find it.
Please tel me your suggestions on how to achive this.
Thanks and Regards,
Varun.K
Hi,
whenever there is a change in the Material Characteristics I need to send the details to another system, we can achive this using Change Pointers but while sending I need to add some extra conditions and change the values as per the conditions where can I do this changes, I have searched for exit in the RBDMIDOC but could not find it.
Please tel me your suggestions on how to achive this.
Thanks and Regards,
Varun.K
2010 Feb 04 10:34 AM
Hi
You can find the relevant customer exits in outbound process code for that message type you are sending the data.
Thanks & Regards
Jyo
2010 Feb 04 1:55 PM
Hi,
Why don't you try to copy the RBDMIDOC to your Z-prog. You can add your own code to the modify the changes and updates.
Thanks,
Ram.
2010 Feb 06 7:08 PM
Hi ,
If you are working ECC 6.0 , Hope Implicit or Explicit Enhancements can help . Develop the code message type specific.
Thanks
Sree
2010 Feb 09 9:12 AM
Hi Varun,
You mentioned Material characteristics, so assume you are talking about Matmas or some enhanced message.Program RBDMIDOC, internally would be calling MASTERIDOC_CREATE_SMD_MATMAS to generate the idocs and you can use the user exits inside the FM.
let me know if it does not help.
Regards,
Siddharth
2014 Aug 22 12:26 PM
Hi Experts ,
Can you let me know the reason for idoc not getting triggered for infotype 105 whenever i change email id. There is Extension ZRMD_A07 created for IDoc HRMD_A . When i run RBDMIDOC it gets triggered for the other infotypes with exception for above infotype 105 . Please suggest.
With regards,
MSK