Estimation time

Former Member
0 Likes
512

Hi Folks,

I need some information to estimation time for interfaces. Based on those estimation guidelines we can decide how complexity is the interface and how many days it will happen to develop that interface. That type of estimation guidelines i need for an interface. Anybody is there to give their valuable suggestions.

Points will be rewarded.

Thanks in advance

1 ACCEPTED SOLUTION
Read only

Former Member
0 Likes
467

Hi,

For Interface the Estimation is like this:

4 Man days work - Simple Object

7 Man days - Medium Object

10 Man days - Complex Object

Regards,

Anji

3 REPLIES 3
Read only

Former Member
0 Likes
468

Hi,

For Interface the Estimation is like this:

4 Man days work - Simple Object

7 Man days - Medium Object

10 Man days - Complex Object

Regards,

Anji

Read only

sreeramkumar_madisetty
Active Contributor
0 Likes
467

Hi

Based on complexity of the object only we can estimate the man hours.

That estimation depends on the organization.

Generally for

simple - 6

medium - 11

complex - 18.

Regards,

kumar

Read only

0 Likes
467

Hi all,

Thanks for your response. Can you tell me which factors they consider while estimating that time.

Thanks in advance