2010 Jan 07 5:16 AM
Hi,
I need to create a dynamic date for my variant.
Date will be the select option - The from date should be the current date and the to date should be current date + 30 days.
When i am using the Selection variant and using the option D to calculate the current date+ 30 days. But that is getting stored in the from date but not in the to-date. My report will be running in back ground every day. So according to the requirment i need to have from date as current date and to-date as current date + 30 days.
I cannot use the logic in initialization as the report will be running based on the variant saved.
Thanks,
Raju
Hi Rajat,
As i mentioned i can not put the logic in Initialization as my report will be running in background every day.
Pls let me know how to save the variant so that i can have both from and to dates in the variant.
Currently i am able to get the current day + 30 days in the from date but i want the from date to be current date and the to date to be current date + 30 days.
Thanks,
Raju
2010 Jan 07 5:38 AM
Hi,
In the event initialization, u need to put values in the date variables.
eg . if you select-option is s_date
then write following code in initialization
s_date-low = sy-datum.
v_date = sy-datum + 30.
s_date-high = v_date
Hope this solves ur problem.
Cheers,
Raj
2010 Jan 07 5:48 AM
Hi Rajat,
As i mentioned i can not put the logic in Initialization as my report will be running in background every day.
Pls let me know how to save the variant so that i can have both from and to dates in the variant.
Currently i am able to get the current day + 30 days in the from date but i want the from date to be current date and the to date to be current date + 30 days.
Thanks,
Raju
2010 Jan 07 6:05 AM
Hi Raju,
Use this function module in your program.
ADD_TIME_TO_DATE.
In this function module, enter the period you need to add to the export parameter I_TIME.
CALL FUNCTION 'ADD_TIME_TO_DATE'
EXPORTING
I_IDATE = SY-DATUM
I_TIME = '30'
I_IPRKZ = ' '
IMPORTING
O_IDATE = date .
WRITE:/ DATE .
Hope it helps.
Regards,
Raj
Edited by: Raj Karunanidhi on Jan 7, 2010 11:36 AM
Edited by: Raj Karunanidhi on Jan 7, 2010 11:37 AM
2010 Jan 07 6:29 AM
Hi Raj,
I can think of one thing,
just use parameters for start date and end date
and then set the their values in the variant as follows,
Press Save on the selection Screen and then put the name and short text then,
in the very last box called "Selection screen objects 1000" check on the fourth check box "Selection variable" for both start date and end date.
Then click on "selection Variable" Button on left hand top corner of the screen.
Then click on the 😧 Dynamic date calculation the must turn Green.
then click on the downward arrow that appears there you will have options to set the date.
there choose current date for the start date and Current date +/- ??? days for the end date.
now while setting the end date it will ask you the number of days there you have to put 30(as it is your requirement) and SAVE.
Then test it .
otherwise you can go for this approach. Keep your date in select-options only and use the following option while selecting "Selection variables"
"Current date - xxx,current date + yyy"
Hope it helps you,
Regards,
Abhijit G. Borkar
Edited by: Abhijit Borkar on Jan 7, 2010 7:31 AM
2010 Jan 07 6:41 AM
Hi,
I have posted a blog on the same topic. Please check below link.
/people/vinod.vemuru2/blog/2010/01/04/how-to-create-a-dynamic-variant-and-setup-batch-job-with-dynamic-variant
Thanks,
Vinod.
2010 Jan 07 6:57 AM
Try this. It will work. I checked it.
AT SELECTION-SCREEN OUTPUT.
REFRESH s_date.
s_date-low = sy-datum.
s_date-high = sy-datum + 30.
APPEND s_date.