2007 Aug 01 10:59 AM
i am uploading a file.
i want to schedule the uploading(conversion) monthly.
what i should do.
please give whole process?
2007 Aug 01 11:03 AM
to schedule the background jobs go to t-code
SM36
regards,
srinivas
<b>*reward for useful answers*</b>
i am uploading a file.
i want to schedule the uploading(conversion) monthly.
what i should do.
please give whole process?
2007 Aug 01 11:03 AM
to schedule the background jobs go to t-code
SM36
regards,
srinivas
<b>*reward for useful answers*</b>
2007 Aug 01 11:47 AM
Hi Javed,
1)Go to SM36 and give job name and job class.
2) Then, go to the start condition -> date/ time tab -> give scheduled start date and time -> then click on period values and select monthly and SAVE.
3) Go to step and give the program name and variant and SAVE.
Hope this helps.
Regards,
Arun Mohan
<b>Note: Reward points if helpful.</b>
2007 Aug 01 9:20 PM
make sure the file is in the application server. program scheduled to run in background cannot access files in presentation server.
as others have suggested you can do this in SM36 and view the spool request in SM37.
you can also go to sa38
1. enter the program name and click on background.
2. enter the variant name and click on schedule
3. give the job name
4. enter the end of month
5. and choose schedule periodically and choose once in every month.
Thanks.