2006 Oct 06 12:11 PM
Hi
I am using CN2W_WBSELEMENT_CREATE_STRU Function module to create WBS element in PS .
i gave PRPS-POSID(wbs number) n PROJ-PSPID(project number) as import parameters.
But i am getting "NO Authorization for profit center action 01 create".
plz help me.
Thanks in advance,
sunitha
Hi
I am using CN2W_WBSELEMENT_CREATE_STRU Function module to create WBS element in PS .
i gave PRPS-POSID(wbs number) n PROJ-PSPID(project number) as import parameters.
But i am getting "NO Authorization for profit center action 01 create".
plz help me.
Thanks in advance,
sunitha
2006 Oct 06 12:13 PM
hi,
I think you need to contact BASIS guys and get the required authorization.
Regards,
Preema
*Reward points for helpful answers
2006 Oct 06 1:17 PM
hi,
try 1st cj11 - same failure?
after that run trx. su53 and mail output to your basis team
A.