‎2008 Jul 15 7:24 AM
Hi Experts,
I need to fetch the commitment and plan amount in my report.
I have asset number, order number and version at my selection screen.On the basis of order number first i am getting OBJNR number from COAS table and then based on this OBJNR number and version i am trying to get the plan and commitment amount from COSP-WTG003 and COOI-ORGWTH table respectively.
But values which i am getting are not correct.
Please let me know what is the correct way to fetch the plan and commitment amount.Do i need to consider value type(WRTTP) also?If yes what should be the value of WRTTP for these amount?
‎2008 Jul 15 9:22 AM
Hi Swati,
generally speaking, for plan values, you should retrieve and add values COSP-WTG001 to COSP-WTG016 (that's 16 values: january, february, ... december, special period 1, special period 2, special period 3, special period 4).
Please keep in mind that you should also restrict your query by COSP-WRTTP = '01' and by COSP-VERSN = your_plan_version.
Also, in COOI you will retrieve individual items, while from COSP you will get total amounts. Please consider which approach is the best for your requirements.
I hope this helps. Kind regards,
Alvaro
‎2008 Jul 15 9:22 AM
Hi Swati,
generally speaking, for plan values, you should retrieve and add values COSP-WTG001 to COSP-WTG016 (that's 16 values: january, february, ... december, special period 1, special period 2, special period 3, special period 4).
Please keep in mind that you should also restrict your query by COSP-WRTTP = '01' and by COSP-VERSN = your_plan_version.
Also, in COOI you will retrieve individual items, while from COSP you will get total amounts. Please consider which approach is the best for your requirements.
I hope this helps. Kind regards,