‎2008 Aug 12 6:06 AM
Hi all,
We have client 90 previously for development and now there is another client 100 for development and all request number and development task moved from client 90 to client 100.
Client 90 is removed now but there are some request that is associated with client 90.
When we want to do some changes in client 100 then there is error for custom table 'Request/task FA1KXXXXX can only be changed in client 90' and when we click ok then it doesn't allow us to change.
Any suggestions welcome,
Regards,
‎2008 Aug 12 6:36 AM
Hi Friend,
You can not change any attributes associated with client 90 in client 100. If you want to change anything in client 100:
Create a request in client 100, include the request which was built in client 90. You can continue with that request. Even if you transport that, request in client 90 will be transported.
Hope it will help you.
Regards
Krishnendu