2007 Jan 16 5:36 PM
Dear Guys
I want to pick data displaying in <b>Current Budget field of CJ30</b>. Can any body tell me the table in which this value stores.
Secondly I want to use all the cost data (Amount) stores in a PS budget which tables can be help ful for this and how I can access them ( i.e link between table).
Basically I am trying to make a report which can show summary of Budget basing on WBS and Netwrok.
2007 Jan 16 5:44 PM
Hi,
CJ30 belongs to KABP dev.class.
Check all the tables in this dev.class and try to do some R&D in finding the required table.
Sorry for this vague reply. This is a way to find out.
Regards
Subramanian
Hi,
CJ30 belongs to KABP dev.class.
Check all the tables in this dev.class and try to do some R&D in finding the required table.
Sorry for this vague reply. This is a way to find out.
Regards
Subramanian
2007 Jan 16 5:44 PM
Hi,
CJ30 belongs to KABP dev.class.
Check all the tables in this dev.class and try to do some R&D in finding the required table.
Sorry for this vague reply. This is a way to find out.
Regards
Subramanian
2007 Jan 16 5:49 PM
Hi Adnan
There are many standard reports for budget/WBS. Please find the T-Codes below,
S_ALR_87013556 - Funds Overview
S_ALR_87013557 - Budget/Actual/Variance
S_ALR_87013558 - Budget/Actual/Commitmt/Rem.Plan/Assg
S_ALR_87013559 - Budget/Distributed/Plan/Distributed
S_ALR_87013560 - Budget updates
S_ALR_87013561 - Availability Control
Regards
Kathirvel