2008 Nov 07 5:03 AM
Hi
Here we are using a BAPI called BAPI_BOM_UPLOAD_SAVE for creating BOM and changing component quantity with change number.During interface project.
while creating or changing a component quantity respective changed quatity is getting displayed but the respective change no is not getting displayed accross the changed quantity.where as while creating thru' CC02 change no is getting displayed .
Can any one give me the soln.
Regards
s.suresh kanna
Hi
Here we are using a BAPI called BAPI_BOM_UPLOAD_SAVE for creating BOM and changing component quantity with change number.During interface project.
while creating or changing a component quantity respective changed quatity is getting displayed but the respective change no is not getting displayed accross the changed quantity.where as while creating thru' CC02 change no is getting displayed .
Can any one give me the soln.
Regards
s.suresh kanna
2008 Nov 07 10:25 AM
Hi All,
we got engineering change management ECM in our project.
mostly BOM components will get changed as per new product development.so change number is used to change BOM component .
for creating change number we use cco1 & in object type we select bom change.
Using that change number we change the BOM component QTY.
while doing with cs02 using change number getting changed qty and respective change number in that particular component row with validity date.
But during interface project like pushing data from legacy system to SAP system. we require BAPI. so we went for BAPI_BOM_UPLOAD_SAVE.while creating BOM and required changes with that BAPI , we are getting changed qty for that particular component but change number is not getting displayed. when we view in cs03
can any one provide solution
Regards
s.suresh kanna