2021 Dec 09 3:25 AM
Hi,
In QA12, While changing the UD(accepted or rejected), material document has been created.
is there any userexit or badi to capture that material document?
Thanks with Regards,
Vallamuthu M.
2021 Dec 09 7:48 AM
Hello vallamuthu.madheswaran2
Material documents resulting from usage decisions are automatically captured under respective inspection lots. Go to QA33, display the inspection lot - there is a button "Material Documents" to display all goods movement for the inspection lot.If you need to trigger additional processing after usage decision material document is posted, check out the MB_DOCUMENT_BADI enhancement.
Best regards
Dominik Tylczynski
2021 Dec 09 7:48 AM
Hello vallamuthu.madheswaran2
Material documents resulting from usage decisions are automatically captured under respective inspection lots. Go to QA33, display the inspection lot - there is a button "Material Documents" to display all goods movement for the inspection lot.If you need to trigger additional processing after usage decision material document is posted, check out the MB_DOCUMENT_BADI enhancement.
Best regards