‎2006 Nov 16 8:42 PM
Hi
I would like to have a batch job running that will collect all the failed WMMBXY idocs in status 51 to be re-processed again. Please let me know a way by which this can be achieved.
Thanks
‎2006 Nov 16 8:53 PM
Hi Suraj,
You can schedule a job to run program RBDMANI2.
Please ensure you have created variant to reprocess message type WMMBXY prior to schedule the job.
Hope this will help.
Regards,
Ferry Lianto
‎2006 Nov 16 8:48 PM
Hi,
You can use the SAP Report RSEOUT00 to re-process the idocs. Fill the selection criteria & save it as varient then schdule the Job using Tcode SM36.
Raja T
‎2006 Nov 16 8:53 PM
Hi Suraj,
You can schedule a job to run program RBDMANI2.
Please ensure you have created variant to reprocess message type WMMBXY prior to schedule the job.
Hope this will help.
Regards,