Basic Start Date and Basic Finished date calculation for backgroung scheduling

Former Member
0 Likes
796

Dears

i need to make this Calculation of  basic dates for backward scheduling,

Basic start date = Basic finish date ( last date ) for work center .

please help me ASAP.

Thanks .

6 REPLIES 6
Read only

Former Member
0 Likes
764

Answer me please ????????????

Read only

VijayaKrishnaG
Active Contributor
0 Likes
764

Hi Eman,

Can you elaborate your query? Please explain where you are facing problem in the above calculation?

Thanks & Regards,

- Vijay

Read only

0 Likes
764

i need add on user exit calculation or condition for basic start date

this calculation is

Basic start date = Basic finish date ( last basic finish date ) for work center .

Thanks

Read only

0 Likes
764

Hi Eman,

Still it's not clear that whether you required any UserExit name to add your calculation or Condition to calculate basic start date.

So please make this clearly.

Thanks

Vijay

Read only

0 Likes
764

this is only user exit for t code iw31

EXIT_SAPLCOIH_012

i need to add my calculation to calculate schedule date in order start from current date and I need to write code for a program or user exit or BAPI to make start date the last finish date of the work center

i hope to clear for u now .

Thanks

Read only

0 Likes
764

please answer me ASAP

Thanks.