‎2010 Oct 17 4:00 PM
Hi All,
During the migration, due to Complexity of our complex BW 3.5 authorization setup we are end up in BI 7 New Design where we have to maintain new Cube to more than 150 Analysis Authorizations each time when we have new Cubes comes.
Do you guys know any method where you can update the new cube to large no of Analysis Authorization (for ex 150) instead of doing manually? Due to complexity of the old design itu2019s very difficult for us to change the new design.
Looking forward for expert opinion.
BR,
Deepak
‎2010 Oct 18 4:06 AM
Hi,
As per my knowledge, it is always recommended to maintain the Analysis authorizations individually. However, you may refer the below thread:
and also the below link:
http://help.sap.com/saphelp_nw73/helpdata/en/c4/057a2de519451faf1819dba4092887/content.htm
Hope this helps!!
Rgds,
Raghu
‎2010 Oct 19 1:42 PM
Thanks Raghu,
Links were helpful, we have developed our program to maintain mass authorization.
BR,
Deepak