Hi All,

I am using BAPI BAPI_PROJECT_MAINTAIN to change my WBS element.It is working fine.I want to change duration field for the activity of the WBS elements. I am using Activity & Activity update tables of the BAPI but it is not updating the fields for the activity.

I am passing WBS Element,duration to be changed,activity & the network.

Network I am passing the AUFNR,

Activity -VORNR

WBS Element-PROJN

duration-calculated one.

It is not updating.Can anyone give some idea where am I missing?

Thank You.

Regards,

K.S.

Moderator message - Moved to the correct forum

Edited by: Rob Burbank on Nov 4, 2010 11:58 AM

Edited by: Kandaswamy S on Nov 10, 2010 8:35 PM

Resolved

Hi All,

I am using BAPI BAPI_PROJECT_MAINTAIN to change my WBS element.It is working fine.I want to change duration field for the activity of the WBS elements. I am using Activity & Activity update tables of the BAPI but it is not updating the fields for the activity.

I am passing WBS Element,duration to be changed,activity & the network.

Network I am passing the AUFNR,

Activity -VORNR

WBS Element-PROJN

duration-calculated one.

It is not updating.Can anyone give some idea where am I missing?

Thank You.

Regards,

K.S.

Moderator message - Moved to the correct forum

Edited by: Rob Burbank on Nov 4, 2010 11:58 AM

Edited by: Kandaswamy S on Nov 10, 2010 8:35 PM

Resolved

1 REPLY 1
Read only

former_member188724
Contributor
0 Likes
394

Resolved