2007 Mar 01 10:29 AM
hi,
i have finished ale customization and processed idoc succesfully!
now i would like to send idoc using change pointers,
i know 3 tranasactin codes bd50,bd,......
i ahve activated change pointers ,messae tyepes,then my doubt is..
If we create a new material in outbound side will it go directly into inbound side
i mean will it need to run bd 10 or not?
i want backgorund schedulilng using change pointer...
could anybody give me some suggetions..
hi,
i have finished ale customization and processed idoc succesfully!
now i would like to send idoc using change pointers,
i know 3 tranasactin codes bd50,bd,......
i ahve activated change pointers ,messae tyepes,then my doubt is..
If we create a new material in outbound side will it go directly into inbound side
i mean will it need to run bd 10 or not?
i want backgorund schedulilng using change pointer...
could anybody give me some suggetions..
2007 Mar 01 11:27 AM
Isn't that set up using transaction BD21? if i remember correctly if you schedule that one it will do the job!
Message was edited by:
Stellan Flinkfeldt
2007 Mar 01 11:28 AM
2007 Mar 01 11:29 AM
Note the changes made on the transaction(i guessed on the first ones)
2007 Mar 01 2:51 PM
As my understanding ur done with activating and configuring the change pointers and now u want to send the idoc to the other system.... so you need to configure the partner profile in WE20 as outbound, once ur done with configuration then you can schedule a batch job for the report RBDMIDOC(BD21) ...once you are done these then you can see the idocs in WE02.
Regards.
2007 Mar 01 5:49 PM
Hi,
After completing the configuration of ale as well as for change pointers, v have to schedule the job. For that v have to go to either SM36 to create a job or SALE --> click on shcedule job.
There is no need for going to that BD10. consider this example, u r changing the material description for a material which is alreading existing using MM02. These changes are stored in the change documents. Change pointers in turn keep track of the changes. As per ur start condition specified in the job description(Background) that job will be automatically started and the material is transferred to the other system as per ur configuration.
First of all clear with the definition of the change pointers.
change pointers techinque is based on the change document technique which keep track of the changes made in the key documents in the sap.
Regards...
Arun.
Reward points if it helps.