Hello, everyone
I was looking for the table, data element, in which the Internal KO01 Plan for SAP was written. Planned through KEP6. As for the actual costs, I can find their value in the COEP table linked to the object number, but only for the actual part (4).
Thank you for any reply
Emilio C
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
CO Planning data (Cost Center, internal orders, wbs a.s.o.) is stored as follows:
if Line-items are activated you find them in the table COEJ and following.
The totals can be found in COSP (Primary) and COSS (secondary) value type 01.
Regards
Holger Homann