Message BK244 - Can't reverse material consumption at PM orders

12-01-2014 1:14 PM
904 views 4 comments
0 Likes
Subscribe

Hello SAP Gurus,

When I reverse confirmation at iw45 transaction code for pm orders, it only reverses activity consumptions but it doesnt reverse the material consumption that I confirmed for pm order. I get this warning message below;

Message BK244 - Not possible to reverse actual costs

Diagnosis

    You have reversed the / confirmation. Actual costs are to be posted for

    this reversal, but there is no cost accounting document for this

    reversed confirmation.

System Response

    No actual costs are posted for the confirmation reversal.

How could I fix this?

Thanks a lot already

sadullah

0 Likes

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Likes

Hi

I just could manage to reverse it by using MB11.

Thanks for all

sadullah

kamalkumar_biswas2
Active Contributor
0 Likes

You can try MB1a through Mov type 262 to reverse the material issued in PM order

varshal_kachole3
Active Contributor
0 Likes

Hi,

Please refer to the recommendations from http://service.sap.com/sap/support/notes/155282

Hope it Helps!

Thanks and Regards,

Varshal Kachole

Former Member
0 Likes

Hi Varshal,

As far as i can see, this oss notes and the other ones that are mentioned it are mostly about activity confirmation whereas my problem is I cant reverse the material confirmation. There is no record in COFC which is sensible since I reversed activity confirmations.

But even though I run iw45 transaction code, i still see material costs at pm order. How could I reverse material confirmations too?

Thanks a lot