Hello All,
I have a business requirement in the MF50. Usually we load the demand weekwise in it.
The requirement from business is, for example i am loading the demand for 1st four weeks Week 1 =10 nos, week 2 = 10nos, week 3=10nos, week4=10 nos,...
Hi,Check the work centers for each activity which was used for confirmation. Also check the standard value key for the work centers in basic data tab and the control key as well.
Hi,Since you mentioned all assemblies are produced in one area itself, you can use single production order and assign different routings to it and confirm accordingly wrt to partial confirmation.also check with your FICO team as well while going on w...
Hi, Naming Convention is all upto business convenience. As i mentioned already, based on the stock maintenance level in your company, you can either maintain it in 1:1 ratio, or keep one storage location and assign the same to different supply areas.