Hello experts,
Revenue recognition for projects needs to be based on PoC (percentage of completion) as per AS 115
Following are the guidelines for revenue recognition:
% Completion = Cost incurred (excluding warranty cost)/ total cost (excludin...
Hello sir,thanks for the reply.can you please share me if you have any document related to RA Method 3 and can you share more details about it.Thanks and regards,Navajyothi Nnavajyothin10@gmail.com
Dear Tejaswi,yes, it is possible to create custom report for S_ALR_87013558 report to see details for multiple projects in one screen.Thanks & regards,Navajyothi N
Hi,In the above mentioned case , as PR is committed against WBS.run t-code CJBV for AVAC activation and try again,if same error repeats then reconstruct AVAC for project with t-code CJBN and they try to create PO.Hope this helps.Thank you.