chart-example.pngScenario:
Currently, P1 is the unique production plant in company.
The material M1 (HALB) is manufactured in production plant P1. Here the type procurement is "E" in plant P1.
The raw material M0 (ROH) is in M1's BOM in plant P...
caetano.almeida and maheshkumar.komatineni,It really doesn't make sense to use only 1 material code for this management level for MRP. I will focus on this organizational policy and restructure it.Thank you very much for your support!
Hi maheshkumar.komatineni,I've tried to structure this at the beginning, but my company doesn't allow me to work with more than 1 material code for manufacturing at the moment (this is a internal policy). We are trying to reverse this. But in parall...