Dear Experts We are experiencing an issue where the automatic GR functionality for production order has stopped. - The control key PP03 is marked with Automatic GR - The production scheduling profile is not assigned to the material master , but at...
Dear Experts
We have created the quality notification, The notification is created for the plant Z , however the rework order created for the notification, belongs to the plant Y.
Please advise , how can we correct this descrepancy
Thanks in ...
Dear Experts
A Quality notification was created and a rework order was assigned to it .
the notification status is as below. the user wants to remove the rework order , assigned to this notification , but is unable to do so.
Kindly render...
Dear Experts
We have a production order which is created during the last fiscal year.
There balances are non zero. The user is unable to apply the deletion flag.
How do we settle and close the order .
Thanks in advance
Scheduling Backward schedulingPlanning strategy :- 10Factory calendar :- 5 working days
Problem :- As per the factory calendar, Saturday and Sunday's are non working day. In the production order, during scheduling, if the start day of productio...
Hi Bramhankar and Prasath Thanks a bunch for the reply I have checked the control key for both the operations 01 & 02Operations 01:- Automatic GR is not assigned Operation 02:- Automatic GR is assigned Could there be any other reason? Thanks