I have a FUBR with splitting all the products by 1 ton. I have a resource with 10 ton capacity So, the scenario is that Product1 can be loaded to this resource with 10 tons, but Product2 can be loaded only with 8 tons (bc volume is ...
Hello experts,
In my road scenario I am using VSR Optimizer to plan FUs. Example, I have a FwO with 1 product = 38 tons. I also have 3 locations:
A - Source location
B - Destination location
Z - Location of all resources
Each ton is a separ...
Hello experts,
In my scenario I don't use coordinates of locations, they were set as default. But I want to use Distance and Duration in transportation lane of my own. For example, I have locations A and B. And there are 200 km between them. I have...
Hi experts,
I created Forwarding order with 1 position (product) and there should be a FUBR.
I also have 4 trucks with capacities 5, 7, 10 and 13 tons. That is why, I don't know how should we split freight units by 5, by 7, by 10 or by 13 tons. I...
Hi Juan,I've tried to use Fix Distance checkbox, and the system fixed the distance = 200 km, but when i press the button of default values of Duration and distance, the system keeped distance = 200 km, but duration is calculated like a time between 2...
Hi René,I am using VSR optimizer. So there can be resources with various capacities from 5 to 30 ton. That is why I should split my FUs by 1 ton. Am I right?Thanks,Georgiy
Hi Marcus and all experts,
This question may be offtop, because I didn't find a suitable topic to write this question, but...
You said, that You used FUBR for splitting, but in fact I'll give an example:
We have 4 resources with capacities 5...