Which SAP standard approach (planning strategy settings etc.) would you use to serve below case?
Two levels of production: FERT and HALB.
FERT materials differentiate only by packaging method, for example 15 FERT materials have 1 HALB ...
Hello,very detailed article, thank you!Which version of SAP S/4HANA was a base to prepare examples and description of functionalities? Best regardsBartłomiej Mazur
Hello 3a9e4ce873a94034b33dc62b0ce600eeThanks for your quick answer.We considered planning strategies without final assembly (5*, 6*), but please notice that in our example FERT material is produced on stock, not when sales order comes. Sounds like M...
Hello,please go to MC7F, find your info structure and tick option in system parameters section: Do not save forecast database.After that system will be able to store your plan in newly created flexible planning table.RegardsBartek