Hello,
A material which is planned in PPDS, we have assigned planning strategy 11, when we execute the MD01N, the planned order generated after netting with available stock. (this should not happen). as if we execute Classic MRP, planned order gene...
Hello,
We have 2020 S4 Hana/EWM, with QM, the GR creates 04 and 17 inspection lot, but if we cancel GR, only 04 inspection lot is cancelled and not the 17.( as of now we are cancelling it manually)
Is there a way, which can cancel the inspection ...
Hello,
I have this particular issue, I settled up, two components, with the same Batch Class, COB1/COB2 is also Identical to the selection and sort class.
Now while creating Process Order, and executing batch determination (manually), the process...
The movement type 101 is set up with Batch classification as 4 at OMJJ, Material is batch managed and classified. One of the Char is marked as "Required"
Now when we execute MB01 for the Purchase order, Batch classification triggers in Fore Ground....
We have set up a control cycle for components with Release Strategy 3.
Source and destination location are EWM managed.
Create Process Order, Release
Execute MF60 with the "EWM Rel Parts" check mark, enter process order as selection
The progr...
Thanks, Raj,As stated all data looks good on the face of it. Apparently the issue is INIOB table has no entry for the material which failed on the determination.Aditya