During STO process from plant A to B.
Std price at A = 80
Std price at B = 100
Freight = 10
Quantity = 1
Following are the accounting entries:
Stock of SFG = - 80
Stock of SFG = 100
Change-in-Stock = - 10 (This must be 20)
Purchase...
Seems like the subcontracting material to be issued is not extended to the Sales area the plant has been configured into.Please use T-code SM30 and access table V_001W_IV.Extend the subcontracting material to the same sales area found in the above-me...
Hi have followed this article step by step and found out that in version management, no matter if the PO is outputted or not, the version management will be triggered.
If the version management is not marked completed after changing qty to higher qt...