Hi experts,
I am new to GATP integration to ECC.
I saw in my new project document that, STO can be created by GATP.
Is it possible to create an STO based on GATP ?
Dear experts, I am trying to edit the route in system to control the delivery dates and facing belowissue. I have route settings as below.
And created a sales order for the above route. Below is the schedule line dates in s...
Hi experts,
I am supporting data migration of customer object in a global roll out project. Customer master data is to be migrated from legacy system to SAP.
In this perspective, there is sales area data of cutomer to be migrated. My que...
Hi Thank you for the quick response Juergen.
I can some how see the calculation happening on entering the dates in the schedule line now. I change the delivery date in schedule line to later date, it shows me the days reflecting in the shipping...
Now if i change to below setting for test purpose.
The new scheduled line dates are reflected on creating new S/O as below.
I can understand the pick pack and load time considered here.
But the transit time time in route is...