Dear Community, I am trying to run MRP on storage location level. I am using reorder point and want MRP to check stock of store location only. So I created a MRP area with particular storage location assigned to that. Then I maintained it in mate...
Hi All, I am having issues with rescheduling of orders in MRP run. I am using strategy 40 in material. Now today is 13.11.2019 and my requirement is: SO/STO- 10 qty- delivery date 11.11.2019 (back date as delivery could not be done or user's in...