We are taking steps to make our moderation process friendlier while ensuring that SAP Community continues to comply with the Digital Services Act (DSA). Learn more in this What’s New post.
Use an Alternate Unit of Measure for the component: PAA ('Pair') or similar, without decimals so that the system rounds to whole units. Assign it to the component with 1 PAA = 2 PC and set it as Unit of Issue. Then maintain the BOM item with quantity...
Phantom assemblies are used for BOM explosion. They are not stockable, they are not shipped nor planned in MRP. You plan, stock, move and consume the components of the phantom and not the phantom.Thus their requirements or the phantom assembly itself...
Is the component set up as phantom assembly (special proc. key 50 or similar) ? And uses planning strategy 'Planning at Phantom Assembly" (strategy 59 or similar)? In this case have a look at the documentation for the planning strategy and reconsider...
The availability overview from comp. ATP check inside CO02 (info how to get there in my first answer) would give a bit more info. Shows the actual ATP result with the req. from the current prod. order as 'simulated requirements'.Anyway: Personally I ...