Hi Aravind and Vinoth,Successor product planning date(SPPD) plus the supplier delivery time to the entry location of BOD = SPRD(Successor Product Receipt Date).As per my understanding SPPD + Planned Delivary time = SPRD.you can maintain Planned de...
Hi Sir,There is no standard report to delete Interchangeability groups or chains in mass in production system.You can use below Z report to delete groups in test systems.Report ZINCMD_DELETE_ALL_GROUPS, using the note 1626688.But In standard process ...
Hi Kannan,DRP does not forward net demand of a predecessor to the successor.This function is not available with a regular supersession chain.Only supersession of type FFF and Remand Seed have such a feature.Best RegardsMallampalli.T
Hi ,Pleeas check in the program /sapapo/saplapoc to find the Product No.length. Decide 18 or 40 number digit. Also you can check whether you want leading zeros and Lexicographical . ThanksMallampalli.T
Hi,Transaction /SCA/PRODACT_OUT should be used to send PROACT data in stead of the report /SCA/DM_TIMESERIES_OUT.Report is basis of other transactions like - /SCA/FCST_OUT- /SCA/PRODACT_OUT The report reads the time series data based on which transac...