Am trying to create a new dynamic date filter but do NOT see the drop-down below Current Date, which shows System Date/Period.
Have System Admin Role
The graphic is below from the documentation, what am I missing?
The DEV system allows, 12 rolling forecast periods, as below: Any suggestions?
However, in PRD system, it switches to 11 Periods, as below:
Date Settings in Model Preferences
Expert
Question about Monthly Forecast Process, using Public & Private Version.
1. Have 3 Public Versions a. Actual b. Plan and 3. Forecast (Category Rolling Forecast) (copy of Plan)
2. Story layouts are based on the Rolling Forecast concept
...
In SAC New Model, have Account Dimension and added a Quantity Measure along with Amount_LC/Amount_GC
When uploading integer values - the Quantity Measure is not available for mapping, only shows Amount_LC/ Amount_GC.
Is this a design limitation o...
Thanks for your prompt response. Funnily it was there for some ittermintent reason, but not now, when I recreate the story.Appreciate your detailed response and the effort.Continue to support the community by your insight and effort.
William, thanks for your comments. Yes, each Planner has an exclusive slice of data, based on Functional Area, there is no overlap. Excepted the above to be standard Planning Workflow.Let me try this actually on Monday.Appreciate your response.
My question is slightly different.
We have 3 Public versions - Actual, Plan, Forecast
We do Rolling Forecast
Question is should our Private Forecast Version be a based on Rolling Forecast Category or Forecast Category?
If our Private Forec...