Hi, I am dealing with S4 HANA 1511 . In our case discount base amount is including unplanned delivery cost. So to exclude it we applied above note. But it is not working. I am not sure if this note hold good as far as HANA is concerned. Is there ...
Hi,I will share the details as below:Assessment cycle created with: Sender - Cost center ( REAL ), Receiver - WBS (REAL), Receiver rule - Fixed percentage.Result - No warning and error. CO currency is populated with posted amountAssessment cycle crea...
Hi,I am running assessment cycle where sender is WBS and receiver is WBS. Receiving WBS is statistical one. So when I was executing cycle it was deriving sender amount but it was not copying that to allocated amount. Also receiver was not picked up b...
Hi,I am not clear about the technical cost element in RA key version. I have given it in RA key for the time being to test but really I am not getting logic for its provision. Further when I am running KKAO I am getting error KJ 148 saying order is n...
Hi,I was wondering if assessment cycle can be used allocate cost of cost center to project (WBS). As we can use assessment to allocate cost from cost center to cost center in that receiver section space for WBS exists. But i learned that there is som...