Hi, to update table /RPM/FIN_PLAN based on transfer table RPM_FIDATA you have to start report /RPM/FICO_INT_PLANNING with execution option "planning".Table /RPM/FIN_PLAN is filled based on the customizing which is maintained in "Portfolio Management ...
Hi Prashanth,Here is the link to the online documentation:https://help.sap.com/viewer/db719753e69f4e8eb9902aaea0fd8471/1909.latest/en-US/48f8a4bc3a4f6b41e10000000a42189c.htmlBest regards,Judith
Hi,To receive data in table DPR_DASHBOARD the "Evaluation"-functionality must be used. You can find information under the following Wiki link https://wiki.scn.sap.com/wiki/display/PLM/Project+Evaluationswith corresponding KBA Note 1889085 to use this...